News
You must understand the operating procedures of using the VICA softening point test machine
Release time:2019-04-10 source:Jinan Hengsi Shanda Instrument Co., Ltd. Browse:
The Vica softening point test machine is mainly used to determine the thermal deformation temperature and Vica softening point temperature of non-metallic materials such as plastics, hard rubber, nylon, electrically insulating materials, long fiber reinforced composite materials, high-strength thermoset laminates and other non-metallic materials. Convenient operation, precise control, extremely intelligent. However, you must understand the operating procedures of using the VICA softening point test machine.
1. The scope of use of thermal deformation Vica softening point test machine: suitable for thermal deformation analysis of non-metallic materials (plastics, rubber, nylon, electrically insulating materials, etc.) and determination of Vica softening point temperature.
2. Quote basis: TH-6020 Vika softening point temperature measurement system user manual.
3. Operating procedures of thermal deformation VICA softening point test machine:
1. Turn on the power supply of the test machine. Before starting the software, first check the installation of the hardware instrument and whether the connection is accurate.
2. Select the test indenter according to the test type, the heat deformation is to be rounded indenter, and the Vika is to be a needle-type indenter. Secure the required indenter to the load rod.
3. Calculate the load according to the test type and the size of the sample:
4. Open the Vika software, the system enters the "Start Screen", press the "Stir" button to complete the zero adjustment before the test, start the test temperature monitoring, deformation calibration, and perform zero adjustment operation before deformation calibration, and the method is formally tested and zeroing.
5. After the parameters are set, press the "Test" key to start the test. Press "Open Report Screen" to observe the deformation, temperature and real-time curve of the sample at any time during the test.
6. When the deformation amount will reach the deformation required for the test, the PLC will automatically record the current temperature in time and display, process and store it through the computer. The system automatically stops the test after the three frames reach the set deformation amount.
4. Without testing, turn off the power supply and unplug the power cord.
5. The test machine and computer cannot access the Internet to avoid poisoning and losing data.
6. Personnel unrelated to the operation of the VIC softening point test machine are not allowed to operate the thermally deformed VIC softening point test machine to avoid damage.
7. Keep the Vika softening point test machine clean and hygienic every day.
Mechanical equipment is essentially the same. Only by mastering the correct method can the entire experimental process be smoother and the experimental data are more accurate. Therefore, you must understand the operating procedures of using the VICA softening point test machine.